top of page

JUDGING THE LOWEST LEVEL

Writer's picture: Mark Turnquest, CIPMMark Turnquest, CIPM

Judging The lowest-level task! To judge the lowest-level task, you should accommodate in your WBS, a willingness to utilize one of the mentioned options, budget or time criteria. The lowest-level task should require at least .25 to 2 percent of the total budget or project time. You also can use segments, such as half or full days, to define the smallest task levels. These approaches may appear initially imprecise, but they establish a general guideline for the lowest-level tasks in your project.


Contact Us In The Bahamas Now!

Join our mailing list

Never miss an update

Email Us

  • Instagram
  • Facebook
  • Twitter
ASHB
OSHA

© 2015 by Green Capital Ltd. - GCL

bottom of page